Operations Management midterm workshop

HUM 4404 · Tuesday 10 November 2026, 2 PM to 3 PM · built from Question Bank 1 for a complete beginner

What's on the midterm

Modules 1 to 3Intro, forecasting and capacity, planning and scheduling
30 marksLearning outcomes CLO1 to CLO3
1 hourTue 10 Nov, 2 PM

Topics by likelihood

TopicLikelihoodTab
Least squares · chase cost · Johnson · EDD/SPTCertainForecasting, Aggregate, Scheduling
MCQ, blanks, true/false, case essayCertainFoundations, Written answers
Forecast errors (MAD, MSE, MAPE) · moving average · smoothingVery likelyForecasting
Utilisation, efficiency, break-even, make or buyVery likelyCapacity
Level vs mixed vs chase costVery likelyAggregate
PPC, capacity factors, planning optionsLikely (theory)Foundations, Capacity
Trend smoothing, seasonal index, tracking signalPossibleForecasting
TOC, supply chain, TQM, leanNot on midtermSkip

Rough split of the 30 marks

An estimate from the bank layout and the teaching plan; it isn't published anywhere.

Bank Q4 is blankLikely one of: forecast-error comparison, capacity/break-even, or level vs chase. The mock has all three.

Study plan: Monday afternoon to Tuesday noon

Exam Tuesday 2 PM. Study stops at 12 noon Tuesday. Short breaks between blocks.

WhenDoDone when
Mon 1:30 to 4What's coming → Foundations → Forecasting (least squares, moving average, smoothing)Formulas for b, a, F(t) from memory
Mon 4:30 to 7Forecast errors (port table) → CapacityMAD 10.31 · break-even 10,000
Mon 8 to 10:30Aggregate planning → SchedulingAl Saleem $27,400 · Johnson 180 min
Mon 10:30 to 11:30Written answers + one pass of recall drills, then sleepMost cards without flipping
Tue 7 to 8Mock under 60 minPaper finished
Tue 8 to 10:30Mark the mock, redo wrong numericals, ask Claude to quiz weak spots, recall drills againWeak topics fixed
Tue 10:30 to 12Cheat sheet · one of each numerical · stop at noonEvery recipe clean
Tue 12 to 2Eat, rest, reach the hall early. No new topicsSeated by 1:50

In the exam hour

Stuck?Ask Claude: "quiz me on capacity", "new Johnson problem, mark my answer", "find my mistake" (paste your table).

Foundations

Operations management = turning inputs into goods and services efficiently.

OM jobs (right answers)

Production planning & controlCapacityLayoutQualityInventorySchedulingMaintenanceSupply chain

Not OM (MCQ traps)

AdvertisingTax collectionPublic relationsRecruitment only

How OM evolved

  1. Craft
  2. Industrial revolution
  3. Taylor: time study
  4. Ford: assembly line
  5. Toyota: TQM, JIT, lean
  6. Now: automation, data, Industry 4.0

PPC: the planning ladder (links the whole midterm)

YearsCapacity planningfacility size, equipment
6 to 18 monthsAggregate planningworkforce, inventory, subcontract
WeeksMaster schedulewhich model, how many
Hours to daysSchedulingjob order on machines

PPC stages: plan → operate → control (feedback against plan).

Productivity

Productivity = Output / Input Labour: 1,200 units / 300 h = 4 per hour Multifactor: (1,200 × $25) / $12,000 = 2.5

Operations strategy

Align operations with business goals. Compete on:

CostQualityDeliveryFlexibility

GoodsServices
Tangible?YesNo
Can store?Yes, inventoryNo, made and used at once
Customer involved?RarelyOften
TrapProductivity is output ÷ input, never the reverse.

Forecasting

Estimate future demand so staff, material and machines are ready in time.

Which method?

Four patterns inside demand data

Least squares: fit a straight line

b = (nΣxy − ΣxΣy) / (nΣx² − (Σx)²) a = ȳ − b·x̄ y = a + bx x = 1…7 → Σx = 28, Σx² = 140, x̄ = 4
Worked: both bank questions

Moving averages lag behind a trend

MethodFormulaUse when
Naivenext = last actualquick baseline
Moving averageΣ last n ÷ nno trend
Weighted MAΣ (w × A) ÷ Σ wrecent data matters more
Worked: shed sales

Exponential smoothing: α sets the reaction speed

F(t) = F(t−1) + α × (A(t−1) − F(t−1)) 142 + 0.2 × (153 − 142) = 144.2 high α = reacts fast · low α = stable demand

Forecast errors: smaller wins

MeasureFormulaTells you
MADΣ|A − F| ÷ naverage miss, in units
MSEΣ(A − F)² ÷ npunishes big misses
RMSE√MSEMSE back in units
MAPEΣ(100|A − F| ÷ A) ÷ naverage miss as %
Worked: Port of Baltimore error tables
TrapsError = actual − forecast · MAPE divides by actual · count only periods that have a forecast.
Possible extras: trend smoothing, seasonal index, regression, tracking signal
Trend smoothing: F = αA + (1−α)(F + T) T = β(F − Fold) + (1−β)T FIT = F + T Seasonal index = season average ÷ overall average Associative = least squares with a cause as x; r from −1 to +1; r² = share explained Tracking signal = Σ errors ÷ MAD (outside limits = biased forecast)

Capacity

Capacity = the most a unit can produce. Match it to forecast demand.

Three capacities, two ratios

Utilisation = actual ÷ design = 64 ÷ 100 = 64%
Efficiency = actual ÷ effective = 64 ÷ 80 = 80%
Worked: cars and pumps (slides)

Break-even: where revenue meets cost

BEP = F ÷ (P − V) = 20,000 ÷ (3 − 1) = 10,000 units

Make or buy

MakeBuy
Cost at 1,000 units20,000 + 10 × 1,000 = AED 30,00027 × 1,000 = AED 27,000 ✓
Switch point20,000 ÷ (27 − 10) = 1,177 units; above it, make

Bottleneck: the slowest step sets the pace

Machines needed

hours needed ÷ hours per machine 5,800 ÷ (250 × 8) = 2.9 → 3

What lowers effective capacity

LayoutSkillsQualityShifts policySchedulingSupplyRegulations

TrapUtilisation ÷ design, efficiency ÷ effective. Efficiency is always the bigger %.

Aggregate planning

Medium-term plan (3 to 18 months): meet forecast demand at the lowest total cost.
StrategyHowMain cost
LevelSame output every month; stock absorbs swingsHolding inventory
ChaseOutput = demand; hire and fire every monthHiring + layoff
MixedMix: steady core + subcontract or overtimeSubcontract / overtime

Same demand, three plans (roofing supplier, units per month)

Worked: roofing plans and Example 5

Chase recipe (bank Q3)

StepDo
1Output per worker per month (Al Saleem: 2 × working days)
2Month 1 need = demand − opening stock; later months = demand
3Workers = need ÷ output per worker, round up
4Up from last month → hire · down → lay off
5Hires × hire cost + layoffs × layoff cost
Worked: Al Saleem ($27,400) and NPI ($22,400)

Capacity options (react)

InventoryHire / lay offOvertimePart-timeSubcontract

Demand options (influence)

Price / promotionBackordersCounter-seasonal products

TrapsOpening stock only in month 1 · output per worker changes with working days · say whether you rounded workers.

Scheduling

Choose the order of jobs to cut waiting, lateness and total time.
TermFormula
Flow timerunning total of processing times
Mean flow timeΣ flow ÷ n
Tardinessmax(0, finish − due)
Makespantime to finish all jobs

One machine: pick a rule

RuleOrder byBest for
FCFSarrivalfairness
SPTshortest job firstlowest mean flow time
EDDearliest due datelateness
LPTlongest job firstrarely best
Worked: TV shop (EDD) and garage (SPT)

Two machines: Johnson's rule

Worked: both bank sets step by step

Tricky true/false

StatementWhy
Least idle time always gives least total timeF"always": bad order can still waste time
Job order affects waiting and completion timeTsee the chart above
Machine fully busy but jobs lateTTV shop: busy all along, 7 of 8 late

5-mark case answers

One frame for every case: define → 3 or 4 levers → result.
CaseLevers (action → effect)Result
Factory
costs, breakdowns, late
Preventive maintenance → less downtime
Planning + sequencing → on-time delivery
Lean → less scrap and waiting
Inventory control → lower holding cost
Lower cost per unit, higher productivity
Hospital
waits, shortages
Capacity matched to arrivals
Rosters built on demand
Reorder points for medicine
Online booking, e-records
Shorter waits, happier patients
Defects
competition, complaints
Process mapping, root cause
Automation (CNC, robots)
SPC charts, TQM
Operator training
Fewer defects, more competitive

Interactive solvers

Type any numbers from a past paper or the mock and the page shows each step. Use them to check your own working, not to replace it; the exam wants the table on paper.

Least squares

Chase strategy

Johnson's rule

Priority rules (FCFS, SPT, EDD, LPT)

Forecast methods and errors (MA, weighted MA, exponential smoothing)

Capacity and break-even

Level against chase (workers per period)

Recall drills

Tap a card to see the answer. Say the answer out loud before you tap. Go through the deck three times; on the third pass you should not need to tap.

Mock exam: 60 minutes, 30 marks

Built from the bank's layout and the topics the teaching plan and slides add. The real paper will be shorter. Part E has one question for every topic that could fill the blank Q4, so treat E2 to E4 as a choice of two if you are short of time.

Part A: multiple choice (1 mark each)

  1. Which of these is an input to a transformation process? (a) Customer satisfaction (b) Raw material (c) Finished car (d) Profit
  2. A firm makes 900 units with 150 labour hours. Labour productivity is (a) 0.17 (b) 6 (c) 750 (d) 1,050 units per hour
  3. Aggregate planning normally covers (a) 1 to 7 days (b) 3 to 18 months (c) 5 to 10 years (d) one shift
  4. Utilisation is actual output divided by (a) effective capacity (b) design capacity (c) demand (d) inventory
  5. Which error measure is expressed as a percentage? (a) MAD (b) MSE (c) RMSE (d) MAPE
  6. Which rule gives the lowest mean flow time on a single machine? (a) FCFS (b) EDD (c) SPT (d) LPT

Part B: fill in the blanks (1 mark each)

  1. The Delphi method is a __________ forecasting technique.
  2. In exponential smoothing, α is called the __________ constant.
  3. The operation with the lowest capacity in a sequence is the __________.
  4. Under a chase strategy the main costs are hiring and __________.
  5. Tardiness is never __________.

Part C: true or false (1 mark each)

  1. On a single machine, changing the job order changes the makespan.
  2. Efficiency can never be lower than utilisation for the same output.
  3. A larger n in a moving average makes the forecast react faster to change.
  4. Opening inventory reduces the production needed in the first month of a chase plan.

Part D: short case (5 marks)

A restaurant chain has long queues at lunch, food waste at night, and staff who are idle in the afternoon. Explain how capacity, workforce scheduling, inventory and technology decisions can fix this.

Part E: numericals

E1. Daily demand for a coffee kiosk over seven days was 98, 110, 131, 140, 162, 175, 190. Derive the least-squares linear forecast equation and forecast day 8.

E2. Monthly demand was 120, 132, 128, 141, 150, 146. For months 4 to 6, compare a 3-month moving average with exponential smoothing (α = 0.3, forecast for month 1 = 118) using MAD and MSE. Which method is better?

E3. A bottling line has a design capacity of 1,200 bottles a shift and an effective capacity of 1,000. Last shift it filled 850. Find utilisation and efficiency. A new product has fixed cost AED 45,000, price AED 12 and variable cost AED 7 per unit: find the break-even volume.

E4. Quarterly demand is 60,000, 90,000, 150,000 and 100,000 units. One worker makes 1,000 units a quarter and the firm starts with 100 workers. Hiring costs $200, firing $400, and holding $0.40 per unit per quarter. Compare a level plan with a chase plan.

E5. Six jobs pass through machine 1 then machine 2 (hours). P: 8, 6. Q: 5, 10. R: 12, 3. S: 4, 11. T: 9, 8. U: 7, 9. Find the Johnson sequence and the minimum total time.

E6. Six jobs A to F have processing times 6, 2, 8, 3, 9, 4 days and due dates 10, 6, 18, 8, 25, 12. Compare FCFS, SPT and EDD on mean flow time and average tardiness.

Show answers

Answer key

A: 1 (b), 2 (b) 900/150 = 6, 3 (b), 4 (b), 5 (d), 6 (c).

B: 1 qualitative, 2 smoothing, 3 bottleneck, 4 layoff (firing), 5 negative.

C: 1 False, the machine runs all jobs back to back whatever the order. 2 True, effective capacity is never above design capacity, so dividing by it gives the larger percentage. 3 False, a larger n smooths more and reacts more slowly. 4 True.

D: Use the hospital frame: capacity (more counters and tables at lunch), workforce (split shifts, fewer staff mid-afternoon), inventory (forecast-based prep, smaller evening batches, first-in-first-out), technology (online pre-orders, kitchen display, sales data to forecast). Close on shorter queues, less waste, lower labour cost.

One-page cheat sheet

BasicsOM turns inputs into outputs efficiently. Inputs → transformation → outputs. Productivity = output ÷ input. Operations strategy lines up operations with business goals. Priorities: cost, quality, delivery, flexibility.
ForecastingQualitative: expert opinion, experience, judgment (Delphi). Time series parts: trend, seasonality, cyclical, random.
b = (nΣxy − ΣxΣy)/(nΣx² − (Σx)²) a = ȳ − b·x̄ y = a + bx
x = 1..7: Σx = 28, Σx² = 140, x̄ = 4.
Aggregate planningMedium term (3 to 18 months). Balance demand with capacity at minimum cost. Decisions: workforce, inventory, production rate, overtime, subcontracting. Chase: workers = ⌈net demand ÷ output per worker⌉. Month 1 net = demand − opening stock. Hire if up, lay off if down.
Johnson's ruleSmallest time left: on M1, place first; on M2, place last. Cross out, repeat. M2 start = max(M1 finish, M2 free). Makespan = last M2 finish.
Priority rulesSPT lowest mean flow time. EDD good for lateness. Flow = running total. Tardiness = max(0, C − due). Mean = total ÷ n. Single machine: makespan same for every rule.
Smoothing and errors
MA = Σ last n / n WMA = Σ w·A / Σ w F(t) = F(t−1) + α(A − F) MAD = Σ|e|/n MSE = Σe²/n RMSE = √MSE MAPE = Σ(100|e|/A)/n
e = actual − forecast. Low α for stable demand.
CapacityUtilisation = actual ÷ design. Efficiency = actual ÷ effective. Machines = hours needed ÷ hours per machine, round up. BEP = F ÷ (P − V). Make or buy: compare F + V·N with price·N. Bottleneck = slowest step sets output.
Plan costingLevel: one rate = total ÷ periods; cost = Σ ending inventory × holding. Mixed: level at minimum need, subcontract the rest. Chase: hire/fire every period. PPC: capacity (years) → aggregate (6 to 18 months) → MPS (weeks) → scheduling (days).
Bank answers